November 15, 2022 - December 30, 2022 (45 days) Closed
Last updated
This approval is for a new Environmental Compliance Approval (air) for Amico Infrastructures Inc., a mobile concrete mix plant that will operate in various locations in the Province of Ontario.
September 16, 2022 - October 31, 2022 (45 days) Closed
Last updated
On November 3, 2023 we issued an amended Environmental Compliance Approval No. A170602 to All Treat Farms Limited to process solid organic waste at a waste disposal site (processing) located at 7963 Wellington Road 109 RR4, Arthur, Wellington North Township, County of Wellington, N0G 1A0.
January 27, 2023 - March 13, 2023 (45 days) Closed
Last updated
Approval is granted for a new Environmental Compliance Approval (industrial sewage) for Good's Realty Inc., for the establishment of stormwater management works, to service proposed auto parts sales and warehouse building development of the site located at 6-8 Wells Street West, in Arthur, Township of Wellington North, County of Wellington, Ontario
Instrument type:
Approval for a consent (subject to conditions) in an area where there is no official plan in place
ERO number
019-7580
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
September 1, 2023 - October 1, 2023 (30 days) Closed
Last updated
Pursuant to Section 53 of the Planning Act, provisional consent was granted on November 6th, 2024, in respect of Application 60-C-231455 for an easement for access purposes on lands described as PIN 42151-0293 in the District of Kenora. The last day this decision can be appealed in November 27th, 2023
Instrument type:
Approval for a consent (subject to conditions) in an area where there is no official plan in place
ERO number
019-7325
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
September 1, 2023 - October 1, 2023 (30 days) Closed
Last updated
Pursuant to Section 53 of the Planning Act, provisional consent was granted on November 6th, 2024 in respect of Application 60-C-201116 for a lot addition for resource-based recreational use on lands described as PIN 42151-0323 & PIN 42151-0293 in the District of Kenora. The last day this decision can be appealed in November 27th, 2023.
November 6, 2023 - December 21, 2023 (45 days) Closed
Last updated
This proposal is for a new Environmental Compliance Approval for a Hydrovac soil processing facility for 1414878 Ontario Inc., located at 3250 Blais Road, Gloucester, Ontario, on a 1.5-hectare heavy industrial zoned site.
August 3, 2023 - September 2, 2023 (30 days) Closed
Last updated
A Permit to Take Water No. 0818-CX4MJF was issued to 140 Yorkville Corporation on October 31, 2023 to amend Permit No. 6104-C99LBA to increase water takings. Water will be taken from one well for construction dewatering purposes, located in the City of Toronto, Ontario, for 26 months.
An amended Environmental Compliance Approval with limited operational flexibility has been issued to Jungbunzlauer Canada Inc. for all sources of air emissions from their facility located at 1555 Elm Street, and 55 Invertose Drive, in Port Colborne.
August 15, 2023 - September 14, 2023 (30 days) Closed
Last updated
Permit to Take Water No. P-300-5236518498 was issued to Mount St. Louis Moonstone Ski Resort Ltd. on November 2, 2023 to renew Permit No. 8615-AQKH4T. Water will be taken from one watercourse and three wells for water supply and snowmaking purposes at the Mount St. Louis Moonstone Ski Resort, located in Moonstone, Ontario, for five years.
November 3, 2023 - December 18, 2023 (45 days) Closed
Last updated
This proposal is for a new Environmental Compliance Approval (air & noise) for C. D. R. Young's Aggregates Inc. for the operation of a mobile operation of a mobile crushing plant.
November 3, 2023 - December 18, 2023 (45 days) Closed
Last updated
This proposal is for a new Environmental Compliance Approval (air & noise) for C. D. R. Young's Aggregates Inc. for the operation of a mobile crushing plant to operate across the Province of Ontario.
We have issued a new Permit to Take Water No. P-300-1201303287 on November 1, 2023, which cancels and replaces Permit No. 0058-9CCKWH, for R. W. Tomlinson Limited for industrial purposes in the Municipality of North Grenville, Ontario. The new permit expires on October 15, 2033
An amended Environmental Compliance Approval has been issued for modifications to the existing stormwater management works serving the Waste Management of Canada Corporation Courtice Transfer and Processing Facility, located at 1 McKnight Road in Courtice, Ontario.
December 28, 2022 - February 11, 2023 (45 days) Closed
Last updated
A new Environmental Compliance Approval has been issued for The Sarjeant Company Limited for industrial stormwater management works, serving a ready mix plant located at 2 Cochrane Lake Road in Seguin Township, Ontario.
February 11, 2022 - March 28, 2022 (45 days) Closed
Last updated
We have amended Environmental Compliance Approval (air & noise) No. 7440-98UGZE for All Treat Farms Limited, a composting, soil blending and packaging facility, located in Arthur, Township of Wellington North, Ontario.
The Director of Exploration has made a decision on the exploration permit application PR-22-000105 to Ring of Fire Metals Proprietary Limited for early exploration activities.
The decision is to: issue the mineral exploration permit
Instrument type:
Changes to the site plan for a pit or quarry
ERO number
019-5660
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
June 21, 2022 - July 21, 2022 (30 days) Closed
Last updated
Approval was granted for a site plan amendment to allow Walker Aggregates Inc. to allow importation of 5,975,000 cubic metres of excess soil in the Town of Fort Erie.