Picton Terminals Ltd. - Permit to take water

Instrument type: Permit to take water

ERO number
019-7454
Ministry reference number
3360-CU6HSG
Notice type
Instrument
Act
Ontario Water Resources Act, R.S.O. 1990
Posted by
Ministry of the Environment, Conservation and Parks
Notice stage
Proposal
Proposal posted
Comment period
August 10, 2023 - September 9, 2023 (30 days) Closed
Last updated

This consultation was open from:

August 10, 2023
to September 9, 2023

Proposal summary

This proposal is for the renewal of Permit to Take Water No. 2802-AS7NGR for Picton Terminals Ltd. Water will be taken from Lake Ontario for construction-dewatering purposes.

Location details

Site address

24 White Chapel Road
Picton, ON
Canada

Site location map

The location pin reflects the approximate area where environmental activity is taking place.

View this location on a map opens link in a new window

Proponent(s)

Picton Terminals Ltd.
24 White Chapel Road
Picton, ON
K0K 2T0
Canada

Proposal details

This proposal is for the renewal of Permit to Take Water No. 2802-AS7NGR for construction purposes. Water will be taken from Lake Ontario. Details of the water taking are as follows:

Permit type – Renewal

Source name: Lake Ontario - shore well

  • purpose: construction
  • maximum rate per minute (litres): 37
  • maximum number of hours of taking per day: 10
  • maximum volume per day (litres): 50,000
  • maximum number of days of taking per year: 60
  • earliest calendar date of taking (mm/dd): 05/01
  • latest calendar date of taking (mm/dd): 11/01
  • period of taking: 5 years

Source name: Lake Ontario - ship loader pump

  • purpose: construction
  • maximum rate per minute (litres): 37
  • maximum number of hours of taking per day: 10
  • maximum volume per day (litres): 50,000
  • maximum number of days of taking per year: 60
  • earliest calendar date of taking (mm/dd): 05/01
  • latest calendar date of taking (mm/dd): 11/01
  • period of taking: 5 years

There are 3 categories of a Permit to Take Water:

  • Category 1: water takings are anticipated to have a lower risk of causing an unacceptable environmental impact/interference
  • Category 2: water takings are anticipated to having a higher potential of causing unacceptable environmental impact or interference
  • Category 3: water takings are anticipated to have the highest potential of causing unacceptable environmental impactor interference

The proposed water taking qualifies as a Category 1 permit.

Supporting materials

View materials in person

Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.

Get in touch with the office listed below to find out if materials are available.

Client Services and Permissions Branch
Address

135 St. Clair Avenue West
Floor 1
Toronto, ON
M4V 1P5
Canada

Office phone number

Comment

Commenting is now closed.

The comment period was from August 10, 2023
to September 9, 2023

Connect with us

Contact

Sign up for notifications

We will send you email notifications with any updates related to this consultation. You can change your notification preferences anytime by visiting settings in your profile page.

Follow this notice