CRH Canada Group Inc. - Permit to take water

Instrument type: Permit to take water

ERO number
019-7290
Ministry reference number
1000226690
Notice type
Instrument
Act
Ontario Water Resources Act, R.S.O. 1990
Posted by
Ministry of the Environment, Conservation and Parks
Notice stage
Decision
Decision posted
Comment period
June 28, 2023 - July 28, 2023 (30 days) Closed
Last updated

This consultation was open from:
June 28, 2023
to July 28, 2023

Decision summary

This proposal for a new Permit to Take Water for CRH Canada Group Inc. was withdrawn. A new proposal was submitted (ERO # 019-7385).

Location details

Site address

10 Dickens Street
Toronto, ON
Canada

Site location map

The location pin reflects the approximate area where environmental activity is taking place.

View this location on a map opens link in a new window

Proponent(s)

CRH Canada Group Inc.
2300 Steeles Avenue West
4th Floor
Concord, ON
L4K 5X6
Canada

Decision details

The proposal for a new Permit to Take Water for CRH Canada Group Inc. was withdrawn. A new proposal was submitted for a new Permit to Take Water (ERO # 019-7385).

A permit has not been issued.

Comments received

Through the registry

0

By email

0

By mail

0
View comments submitted through the registry

Supporting materials

View materials in person

Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.

Get in touch with the office listed below to find out if materials are available.

Client Services and Permissions Branch
Address

135 St. Clair Avenue West
Floor 1
Toronto, ON
M4V 1P5
Canada

Office phone number

How to Appeal

Appeals are not allowed

No decision was made.

Connect with us

Contact

Sign up for notifications

We will send you email notifications with any updates related to this consultation. You can change your notification preferences anytime by visiting settings in your profile page.

Follow this notice

Original proposal

ERO number
019-7290
Ministry reference number
1000226690
Notice type
Instrument
Act
Ontario Water Resources Act, R.S.O. 1990
Posted by
Ministry of the Environment, Conservation and Parks
Proposal posted

Comment period

June 28, 2023 - July 28, 2023 (30 days)

Proposal details

This proposal is for a new Permit to Take Water for CRH Canada Group Inc.Water will be taken from one well for the construction dewatering purposes for the Lakeshore East Joint Corridor project, located in the City of Toronto, Ontario Details of the water taking are as follows:

Source name: RW1 & Gerrard Station West

  • purpose of taking: construction dewatering
  • maximum rate per minute (litres): 310
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres):445,000
  • maximum number of days of taking per year: 365
  • period of water taking: January 1 to December 31 for 10 years

Source name: RW2

  • purpose of taking: construction dewatering
  • maximum rate per minute (litres): 14
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 20,000
  • maximum number of days of taking per year: 365
  • period of water taking: January 1 to December 31 for 10 years

Source name: RW3

  • purpose of taking: construction dewatering
  • maximum rate per minute (litres): 58
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 83,000
  • maximum number of days of taking per year: 365
  • period of water taking: January 1 to December 31 for 10 years

Source name: RW4

  • purpose of taking: construction dewatering
  • maximum rate per minute (litres): 87
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 124,000
  • maximum number of days of taking per year: 365
  • period of water taking: January 1 to December 31 for 10 years

Source name: RW5 & Leslieville Station East

  • purpose of taking: construction dewatering
  • maximum rate per minute (litres): 74
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 106,000
  • maximum number of days of taking per year: 365
  • period of Water Taking: January 1 to December 31 for 10 years

Source name: RW6 & Leslieville Station West

  • purpose of taking: construction dewatering
  • maximum rate per minute (Litres): 187
  • maximum number of hours of taking per day: 24
  • maximum volume per day (Litres): 269,000
  • maximum number of days of taking per year: 365
  • period of water taking: January 1 to December 31 for 10 years

Source name: RW7

  • purpose of taking: construction dewatering
  • maximum rate per minute (litres): 165
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 237,000
  • maximum number of days of taking per year: 365
  • period of water taking: January 1 to December 31 for 10 years

Source name: RW8

  • purpose of taking: construction dewatering
  • maximum rate per minute (litres): 64
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 92,000
  • maximum number of days of taking per year: 365
  • period of water taking: January 1 to December 31 for 10 years

Source name: RW9

  • purpose of taking: construction dewatering
  • maximum rate per minute (litres): 314
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 451,000
  • maximum number of days of taking per year: 365
  • period of water taking: January 1 to December 31 for 10 years

Source name: RW10

  • purpose of taking: construction dewatering
  • maximum rate per minute (litres): 64
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 92,000
  • maximum number of days of taking per year: 365
  • period of water taking: January 1 to December 31 for 10 years

Source name: RW11

  • purpose of taking: construction dewatering
  • maximum rate per minute (litres): 55
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 79,000
  • maximum number of days of taking per year: 365
  • period of water taking: January 1 to December 31 for 10 years

Source name: RW12

  • purpose of taking: construction dewatering
  • maximum rate per minute (litres): 35
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 50,000
  • maximum number of days of taking per year: 365
  • period of water taking: January 1 to December 31 for 10 years

Source name: Queen GO Bridge (2 Abutments)

  • purpose of taking: construction dewatering
  • maximum rate per minute (litres): 20
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 28,000
  • maximum number of days of taking per year: 365
  • period of water taking: January 1 to December 31 for 10 years

Source name: Dundas Bridge P2 (2 Abu,1 Pier)

  • purpose of taking: construction dewatering
  • maximum rate per minute (litres): 49
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 70,000
  • maximum number of days of taking per year: 365
  • period of water taking: January 1 to December 31 for 10 years

Source name: Dundas Bridge P3 (2 Abu,1 Pier)

  • purpose of taking: construction dewatering
  • maximum rate per minute (litres): 62
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 89,000
  • maximum number of days of taking per year: 365
  • period of water taking: January 1 to December 31 for 10 years

Source name: Logan Bridge P2 (2 Abu, 1 Pier)

  • purpose of taking: construction dewatering
  • maximum rate per minute (litres): 241
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 347,000
  • maximum number of days of taking per year: 365
  • period of water taking: January 1 to December 31 for 10 years

Source name: Logan Bridge P3 (2 Abu, 1 Pier)

  • purpose of taking: construction dewatering
  • maximum rate per minute (litres): 273
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 392,000
  • maximum number of days of taking per year: 365
  • period of water taking: January 1 to December 31 for 10 years

There are 3 categories of a Permit to Take Water:

  • Category 1: water takings are anticipated to have a lower risk of causing an unacceptable environmental impact/interference
  • Category 2: water takings are anticipated to having a higher potential of causing unacceptable environmental impact or interference
  • Category 3: water takings are anticipated to have the highest potential of causing unacceptable environmental impactor interference

The proposed water taking qualifies as a Category 3 permit.

Supporting materials

View materials in person

Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.

Get in touch with the office listed below to find out if materials are available.

Client Services and Permissions Branch
Address

135 St. Clair Avenue West
Floor 1
Toronto, ON
M4V 1P5
Canada

Office phone number

Comment

Commenting is now closed.

This consultation was open from June 28, 2023
to July 28, 2023

Connect with us

Contact