Approval was granted to Sturgeon Falls Brush and Contracting Limited to establish and operate a sawmill facility near Sturgeon Falls, Ontario.
Location details
Site location details
The Municipality of West Nipissing in the District of Nipissing.
Patent lands at 12471 Highway 17E, Sturgeon Falls, Ontario, on Lot 9 Con 2, Pedley Township, District of Nipissing.
Proponent(s)
Sturgeon Falls Brush and Contracting Limited
145 Main Street
Suite 425
Sturgeon Falls ,
ON
P2B 1N8
Canada
Decision details
On December 22, 2022 we made a decision to issue a Type “C” Forest Resource Processing Facility Licence to Sturgeon Falls Brush and Contracting Limited to construct and operate a facility for a term of five years.
Effects of consultation
There were no comments submitted as a result of consultation.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
5520 Hwy 101 East, 2nd Floor
PO Bag 3020
South Porcupine,
ON
P0N 1H0
Canada
How to Appeal
Appeals are not allowed
This instrument type cannot be appealed. Learn more about our consultation process.
Connect with us
Contact
Heather Farrer
5520 Hwy 101 East, 2nd Floor
PO Bag 3020
South Porcupine,
ON
P0N 1H0
Canada
Original proposal
Proposal details
The Ministry of Natural Resources and Forestry is considering the issuance of a type “C” forest resource processing facility licence to authorize the construction and operation of a forest resource processing facility.
Under Ontario Regulation 167/95 under the Crown Forest Sustainability Act, a type “C” licence is issued for a “sawmill” with the capacity to consume between 25 and 200 cubic metres per eight-hour shift. Typical products include lumber, sawdust, bark, by-product chips, etc. A forest resource processing facility licence may be issued for a term of up to five years.
Other information
Sturgeon Falls Brush and Contracting Limited has submitted a proposal to establish and operate a sawmill facility. The facility is to be constructed on the company’s property located east of Sturgeon Falls, Ontario. The proposal involves the construction and operation of a sawmill facility which will include equipment necessary for receiving fibre, debarking, sawing, planing, and chipping/creating shavings. The new sawmill is intended to replace an existing smaller sawmill currently operating on the same property. The company plans to maintain the existing sawmill which may operate intermittently, and it will also continue operating a fuelwood processor and cedar mulch business at the same site.
The proponent is proposing to consume private land and Crown forest resources. Harvesting of forest resources in a Crown forest will be conducted in accordance with approved Forest Management Plans. Harvesting of trees reserved to the Crown on patented or privately-owned lands will be conducted in accordance with a licence to Harvest granted under Ontario Regulation 167/95.
The sawmill is expected to consume approximately 7,000 cubic metres of primarily poplar and hemlock forest resources annually. Other species such as cedar, white birch, tolerant hardwood, red and white pine, and spruce-pine-fir may also be processed at the sawmill.
Products will include:
- lumber for the building of swamp mats
- skids used in utility construction projects
- custom order rough and planed lumber
- decking
- dock and siding materials
- fuelwood
The wood supply will be primarily sourced from land clearing projects undertaken by Sturgeon Falls Brush and Contracting Limited and via the purchase of open market fibre from local Crown forests such as the Nipissing Forest. The sawmill will continue to employ five to seven staff and will operate year-round.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
5520 Hwy 101 East, 2nd Floor
PO Bag 3020
South Porcupine,
ON
P0N 1H0
Canada
Comment
Commenting is now closed.
This consultation was open from August 15, 2022
to September 14, 2022
Connect with us
Contact
Heather Farrer
5520 Hwy 101 East, 2nd Floor
PO Bag 3020
South Porcupine,
ON
P0N 1H0
Canada
Comments received
Through the registry
0By email
0By mail
0