Decision summary
The ministry has closed this file (#2967-C2AU3S) as the application was incomplete.
Location details
Site address
72 Ann Street
London,
ON
Canada
Site location map
The location pin reflects the approximate area where environmental activity is taking place.
View this location on a map opens link in a new windowProponent(s)
Co-Fo Concrete Forming Construction Limited
72 Ann Street
London,
ON
N6A 1P9
Canada
Decision details
The application for an Environmental Compliance Approval for industrial stormwater management works was found incomplete.
The ministry closed this file on September 6, 2023 and has not issued an approval.
When and if the applicant submits a revised application, the ministry will post a notice of proposal.
Effects of consultation
No comments were received.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
How to Appeal
Appeals are not allowed
As no decision was made, there is no decision to appeal.
Connect with us
Contact
Client Services and Permissions Branch
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada
Original proposal
Proposal details
The proposal is for a new Environmental Compliance Approval for industrial storm water management works serving CO-FO Concrete Forming Construction Limited, located at 72 Ann Street in the City of London.
The storm water management works comprise of storm water quality and quantity control, consisting of:
- on-site grading to direct storm water runoff to one catch basin located on the west side of the main building
- an existing storm water containment area (wet pond) located on the west side of the site
- two oil water separators
Collected non-contact storm water and post-treatment storm water shall be directed to existing storm sewers located along Ann Street or existing City of London drain.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
Comment
Commenting is now closed.
This consultation was open from August 20, 2021
to October 4, 2021
Connect with us
Contact
Client Services and Permissions Branch
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada
Comments received
Through the registry
0By email
0By mail
0