Update Announcement
This proposal notice is being updated on May 13, 2020 to advise the public that the permit application is still under review and the Ministry is considering concerns raised by an Aboriginal community which warrant additional time to adequately consider. The original proposal date and comment period have not been altered. The anticipated date of decision will be within 30 days of the lifting of the state of emergency relating to COVID-19.
This consultation was open from:
March 18, 2020
to April 17, 2020
Decision summary
The Director of Exploration has made a decision on the exploration permit application PR
The decision is to Issue.
Location details
Site location details
To view individual claims on a map please use the Mining Lands Administration System. Click on “I want to…” and select “Find a claim” to search by claim numbers or "Find a township" to search by township.
The mining claims are located approximately 21 kilometers south of Cochrane Ontario, in Duff and Mann Townships, District of Cochrane, North East Region.
Mining Claims/Leases: 566835, 574447, 574448, 574449, 574450, 574451, 574452, 574453, 574454, 574455, 574456, 575225, 575226, 575227, 575228, 578978, 578979, 578980, 578981, 578982, 578983, 578984, 578985, 579291, 579449, 579450
Site location map
The location pin reflects the approximate area where environmental activity is taking place.
View this location on a map opens link in a new windowProponent(s)
C. Cox
Postal Box 792
Kirkland Lake,
ON
P2N 3K4
Canada
Decision details
On September 18, 2020 the ministry issued an exploration permit approximately 21 kilometers south of Cochrane Ontario, in Duff and Mann Townships, District of Cochrane, North East Region to conduct early exploration activities.
This permit will allow the company to conduct
- mechanized drilling (greater than 150 kilograms)
- mechanized stripping (greater than 100 square metres in a 200 metres radius)
- pitting and trenching of bedrock (greater than 3 cubic metres in a 200 metre radius)
- geophysical survey requiring generator
- line cutting (less than 1.5-meter width)
The exploration permit was issued once all Indigenous communities and the public had the opportunity to provide comment or raise their concerns. The issued exploration permit is valid for a period of three years from the date of issue.
Effects of consultation
No comment was received through the Environmental Registry of Ontario resulting in no impact on the decision to proceed or not with this proposal.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
5520 Highway 101 E Highway
PO Box 3060
South Porcupine Ontario,
ON
P0N 1H0
Canada
How to Appeal
Appeals are not allowed
This instrument type cannot be appealed. Learn more about our consultation process.
Connect with us
Contact
Amy Blaser
5520 Highway 101 E Highway
PO Box 3060
South Porcupine Ontario,
ON
P0N 1H0
Canada
Original proposal
Proposal details
C. Cox has submitted an application to the ministry for an exploration permit as required under the Mining Act for the following early exploration activities:
- mechanized Drilling (greater than 150 kilograms)
- mechanized Stripping (greater than 100 square metres in a 200 metres radius)
- pitting and Trenching of Bedrock (greater than 3 cubic metres in a 200 metre radius)
- geophysical Survey Requiring Generator
- line Cutting (less than 1.5 meters width)
This notice is provided to receive comments that can be considered in the decision-making process prior to the issuance of an exploration permit.
An Exploration Permit does not relieve the proponent from compliance with any other requirements that are set out under the Mining Act or any other Act. All activities included in the Exploration Permit proposal must be carried out in compliance with Ontario Regulation 308/12 and the Provincial Standards for Early Exploration. The Exploration Permit duration will be up to 3 years.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
5520 Highway 101 E Highway
PO Box 3060
South Porcupine Ontario,
ON
P0N 1H0
Canada
Comment
Commenting is now closed.
This consultation was open from March 18, 2020
to April 17, 2020
Connect with us
Contact
Amy Blaser
5520 Highway 101 E Highway
PO Box 3060
South Porcupine Ontario,
ON
P0N 1H0
Canada
Comments received
Through the registry
0By email
0By mail
0