Glencore Canada Corporation - Changes to the site plan for a pit or quarry

Instrument type: Changes to the site plan for a pit or quarry

ERO number
013-4826
Ministry reference number
MNRF INST 12/19
Notice type
Instrument
Act
Aggregate Resources Act, R.S.O. 1990
Posted by
Ministry of Northern Development, Mines, Natural Resources and Forestry
Transferred to
Ministry of Natural Resources and Forestry
Notice stage
Decision
Decision posted
Comment period
March 7, 2019 - April 6, 2019 (30 days) Closed
Last updated

This consultation was open from:
March 7, 2019
to April 6, 2019

Decision summary

Approval was granted for a site plan amendment to allow Glencore Canada Corporation to increase the extraction area for Licence No. 86635, operating in the City of Greater Sudbury.

Location details

Site location details

Part Lot 3, Concession 5, Geographic Township of Fairbank, City of Greater Sudbury

This site is Aggregate Resources Act (ARA) Licence No. 86635 and is located at the southeast end of Vermillion Lake.

A link to our mapping tool allows you to locate and view licensed site under the ARA.

Site location map

The location pin reflects the approximate area where environmental activity is taking place.

View this location on a map opens link in a new window

Proponent(s)

Glencore Canada Corporation
2 Longyear Drive
Falconbridge, ON
P0M 1S0
Canada

Decision details

The changes to the site plan for ARA Licence No. 86635 were approved by the Regional Director on September 7, 2021. This approval will enable the following:

  • extraction setback along the west boundary reduced to 0 metres
  • extraction setback along the east boundary reduced to 0m along the western edge of the Lockerby Mine access road
  • the extraction area increased to 21.3 ha, including the south end of the licensed site
  • variance of operational standard 5.19 varied to allow the final rehabilitated faces to be sloped to 3:1 or to natural bedrock where encountered

A copy of the approved site plan for this licenced site can be obtained from the contact identified below.

Comments received

Through the registry

0

By email

2

By mail

0
View comments submitted through the registry

Effects of consultation

No comments were received in response to the Environmental Registry notice.

Two comments were received through the ARA consultation process. The Ministry of Northern Development, Mines, Natural Resources and Forestry requested further information and supplemental work be completed to assess the presence of Species at Risk and fish habitat on the site.

As of April 1, 2019, full operational responsibility for Species at Risk was transferred to the Ministry of Environment, Conservation and Parks (MECP). As such, outstanding comments related to Species at Risk were referred to MECP for resolution. Species at Risk were assessed by the applicant as part of the amendment request and identified potential habitat for Eastern Whip-poor-will within the proposed area of extraction. This habitat was registered with MECP under Section 23.14 of Ontario Regulation 242/08.

The Department of Fisheries and Oceans requested a self-assessment to evaluate the presence of and impact to fish habitat.

The proponents addressed all comments by providing additional information and revising the site plan. All concerns were addressed at the end of the process.

Supporting materials

View materials in person

Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.

Get in touch with the office listed below to find out if materials are available.

MNDMNRF - ROD - Integrated Aggregate Operations Section
Address

300 Water Street, 4th Floor South tower
Peterborough, ON
K9J 3C7
Canada

How to Appeal

Appeals are not allowed

This instrument type cannot be appealed. Learn more about our consultation process.

Connect with us

Contact

Jason McLay

Phone number
Email address
Office
MNDMNRF - ROD - Integrated Aggregate Operations Section
Address

300 Water Street, 4th Floor South tower
Peterborough, ON
K9J 3C7
Canada

Sign up for notifications

We will send you email notifications with any updates related to this consultation. You can change your notification preferences anytime by visiting settings in your profile page.

Follow this notice

Original proposal

ERO number
013-4826
Ministry reference number
MNRF INST 12/19
Notice type
Instrument
Act
Aggregate Resources Act, R.S.O. 1990
Posted by
Ministry of Natural Resources and Forestry
Proposal posted

Comment period

March 7, 2019 - April 6, 2019 (30 days)

Proposal details

Proposal updates

This notice was updated on March 31, 2021 to advise the public that there has been no change to the status of the proposal and it is still being considered.  No additional opportunity for comment is being provided for at this time.

Description of instrument

Glencore Canada Corporation has applied to amend their site plan for Aggregate Licence #86635. They are requesting an expansion of the extraction area within the licenced boundary. They are also requesting the elimination of the 15-meter setback on the west boundary of the licence that abuts an adjacent property that is also owned by Glencore and the 30-meter setback that abuts their private road to the east. As well, they are proposing to allow for a variance to the Aggregate Resources of Ontario Provincial Standards, Operational Standards 5.19.1 to allow for the final rehabilitated faces to be sloped to 3:1 or to natural bedrock where it is encountered.

Other information

Glencore Canada Corporation operates this site under the authority of Licence #86635 under the Aggregate Resources Act.

Site Plan information is available to view at the Ministry’s Sudbury District office. Making an appointment to view the information is recommended to ensure aggregate staff will be available to provide information and answer questions.

A link to the Aggregate Resources Act is provided http://www.ontario.ca/laws/statute/90a08

Other public consultation opportunities:

The proposal request for this licence is being circulated within the Ministry’s Sudbury District office. Additionally, notification of this application has been forwarded to the City of Greater Sudbury, Nickle District Conservation Authority, Ministry of Environment, Conservation and Parks, Department of Fisheries and Oceans and landowners within 120 meters of the licence boundary for comment.

Supporting materials

View materials in person

Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.

Get in touch with the office listed below to find out if materials are available.

MNRF - ROD - Integrated Aggregate Operations Section
Address

300 Water Street
4th Floor, South tower
Peterborough, ON
K9J 3C7
Canada

Comment

Commenting is now closed.

This consultation was open from March 7, 2019
to April 6, 2019

Connect with us

Contact

Jason McLay

Phone number
Email address
Office
MNRF - ROD - Integrated Aggregate Operations Section
Address

300 Water Street
4th Floor, South tower
Peterborough, ON
K9J 3C7
Canada