This consultation was open from:
October 20, 2017
to December 4, 2017
Decision summary
Massilly North America Incorporated has requested to withdraw their application for an amendment to the Limited Operational Flexibility for Environmental Compliance Approval (Air & Noise) No. 2561-9LVQXM.
Location details
Site address
406 Elgin Street
Brantford,
ON
N3S 7P6
Canada
Site location map
The location pin reflects the approximate area where environmental activity is taking place.
View this location on a map opens link in a new windowProponent(s)
Massilly North America Incorporated
406 Elgin Street
Brantford,
ON
N3S 7P6
Canada
Decision details
This proposal was for an amendment to the Limited Operational Flexibility for an Environmental Compliance Approval (Air & Noise) No.2561-9LVQXM a container cap closures manufacturing facility located in the City of Brantford, County of Brant.
At the request of Massilly North America Incorporated, we have withdrawn their amendment to the Limited Operational Flexibility for an Environmental Compliance Approval (Air & Noise) No.2561-9LVQXM and have closed the file.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada
How to Appeal
Appeals are not allowed
There is no mechanism to appeal an application which has been withdrawn.
Connect with us
Contact
Client Services and Permissions Branch
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada
Original proposal
Proposal details
This proposal is for an amendment to the Limited Operational Flexibility for an Environmental Compliance Approval (Air & Noise) No. 2561-9LVQXM for Massilly North America Inc., a container cap closures manufacturing facility located in the City of Brantford, County of Brant.
The emission sources from the manufacturing and associated processes that exhaust to the air include cap liner processing lines, coating lines, curing lines, materials storage, and maintenance welding activities.
The amendment includes the addition of cap liner processing lines.
Emissions to the air from this facility include napthalene, silicone, formaldehyde, nitrogen oxides, and noise.
The Environmental Compliance Approval with Limited Operational Flexibility (Air), when issued, permits modifications to the facility subject to limits on operational flexibility that include a production limit for the facility to be specified on the Environmental Compliance Approval with Limited Operational Flexibility (Air).
The limited operational flexibility conditions have an expiry date. The company will be required to make an application for amendment at that time to renew these conditions.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada
Comment
Commenting is now closed.
This consultation was open from October 20, 2017
to December 4, 2017
Connect with us
Contact
Client Services and Permissions Branch
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada
Comments received
Through the registry
0By email
0By mail
0