Cette consultation a eu lieu :
du 14 septembre 2017
au 14 octobre 2017
Résumé de la décision
A permit to take water was not required.
Détails de l'emplacement
Adresse du site
Blind River Hydroelectric station
Causley St, Blind River
Algoma,
ON
P0R 1B0
Canada
Détails de l'emplacement du site
GeoReference: Map Datum: NAD83
Zone: 17
Accuracy Estimate: 10-30 metres
eg. Medium Quality GPS, Method: GPS
UTM Easting: 349084, UTM Northing: 5116497
UTM Location Description: near gate to the power house
Site #: 1643-ALUHQT
Carte de l'emplacement du site
L'épingle de localisation correspond à la zone approximative où a lieu l’activité environnementale.
Afficher cet emplacement sur une carte opens link in a new windowPromoteur(s)
North Shore Power Group Incorporated
80 Development Drive
Sault Ste. Marie,
ON
P0R 1B0
Canada
Détails de la décision
Amendments to the Ontario Water Resources Act (OWRA) made on April 1, 2020 removed the need for a permit to take water for the construction or operation of a dam for the purposes of generating electricity.
This activity no longer requires a permit and none was issued.
The ministry advised the applicant that no permit was required on August 26, 2020.
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
435 James Street South
Floor 3, Suite 331
Thunder Bay,
ON
P7E 6S7
Canada
135 St Clair Ave W
Toronto,
ON
M4V 1P5
Canada
How to Appeal
Appeals are not allowed
As no decision was made, there is no decision to appeal.
Communiquer avec nous
Contact
Permit to take water coordinator (Northern region)
435 James Street South
Floor 3, Suite 331
Thunder Bay,
ON
P7E 6S7
Canada
Proposition initiale
Détails de la proposition
Description of instrument
This application is for a new Permit to Take Water for Blind River Dam Generating Station.
The water taking will be as follows:
- Source Name: Blind River Dam G.S
- Source of Water: Blind River
- Purpose of taking: Power Generation
- Maximum rate per minute (litres per minute): 244,920
- Maximum number of hours of taking per day: 24
- Maximum Volume of taking per day: 352, 684, 800 Litres
- Maximum number of days of taking in a year: 365
- Period of Water Taking:
- Earliest calendar date of taking (mm/dd): 01/01
- Latest calendar date of taking (mm/dd): 12/31
- Length of taking: 10 years
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
435 James Street South
Floor 3, Suite 331
Thunder Bay,
ON
P7E 6S7
Canada
Commentaire
La consultation est maintenant terminée.
Cette consultation a eu lieu 14 septembre 2017
au 14 octobre 2017
Communiquer avec nous
Contact
Permit to take water coordinator (Northern region)
435 James Street South
Floor 3, Suite 331
Thunder Bay,
ON
P7E 6S7
Canada
Commentaires reçus
Par l'entremise du registre
0Par courriel
0Par la poste
0