This consultation was open from:
January 30, 2019
to March 1, 2019
Decision summary
We have not approved a new Permit to Take Water for Coon Bros. Sand & Gravel (1988) Limited for the purposes of dewatering, dust suppression and wash pond (pits and quarries). The application was returned to the proponent on February 7, 2019 because it was incomplete. No permit was issued.
Location details
Site address
400 Jones Road
Gravenhurst,
ON
P1P 1R1
Canada
Site location details
Lot 17, Concession 6.
Site location map
The location pin reflects the approximate area where environmental activity is taking place.
View this location on a map opens link in a new windowProponent(s)
Coon Bros. Sand & Gravel (1988) Limited
400 Jones Road
Gravenhurst,
ON
P1P 1R1
Canada
Decision details
We have not approved a new Permit to Take Water for Coon Bros. Sand & Gravel (1988) Limited for the purposes of dewatering, dust suppression and wash pond (pits and quarries).
The application was returned to the proponent on February 7, 2019 because it was incomplete.
No permit was issued.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
5775 Yonge Street
Floor 8
Toronto,
ON
M2M 4J1
Canada
How to Appeal
Appeals are not allowed
There is no mechanism for appeal for a returned application.
Connect with us
Contact
Permit To Take Water Coordinator (Central Region)
5775 Yonge Street
Floor 8
Toronto,
ON
M2M 4J1
Canada
Original proposal
Proposal details
Description of instrument
This proposal is for a new Permit to Take Water for Coon Bros. Sand & Gravel (1988) Limited to take water from two (2) ponds for the purposes of dewatering, dust suppression and wash pond (pits and quarries). The water taking is as follows:
Source Name: Quarry - Sump (Spring and Major Rainfall Event Pumping)
- Purpose of taking: construction/dewatering
- Maximum rate per minute (litres per minute): 1,718
- Maximum number of hours of taking per day: 24
- Maximum Volume of taking per day: 2,474,567 Litres
- Maximum number of days of taking in a year: 60
- Earliest calendar date of taking (mm/dd): 04/01
- Latest calendar date of taking (mm/dd): 11/30
- Length of taking: 10 years
Source Name: Quarry -Sump (Typical Operational Rainfall Event Pumping)
- Purpose of taking: construction/dewatering
- Maximum rate per minute (litres per minute): 705
- Maximum number of hours of taking per day: 24
- Maximum Volume of taking per day: 1,014,000 Litres
- Maximum number of days of taking in a year: 90
- Earliest calendar date of taking (mm/dd): 05/01
- Latest calendar date of taking (mm/dd): 11/30
- Length of taking: 10 years
Source Name: Quarry - Crusher Plant Dust Suppression
- Purpose of taking: construction/dewatering
- Maximum rate per minute (litres per minute): 43
- Maximum number of hours of taking per day: 14
- Maximum Volume of taking per day: 36,120 Litres
- Maximum number of days of taking in a year: 240
- Earliest calendar date of taking (mm/dd): 05/01
- Latest calendar date of taking (mm/dd): 11/30
- Length of taking: 10 years
Source Name: Quarry - Closed Loop Wash Pond
- Purpose of taking: construction/dewatering
- Maximum rate per minute (litres per minute): 44.2
- Maximum number of hours of taking per day: 24
- Maximum Volume of taking per day: 63,648 Litres
- Maximum number of days of taking in a year: 30
- Earliest calendar date of taking (mm/dd): 05/01
- Latest calendar date of taking (mm/dd): 11/30
- Length of taking: 10 years
Source Name: Quarry - Internal Road and Stockpile Dust Suppression
- Purpose of taking: construction/dewatering
- Maximum rate per minute (litres per minute): 94.5
- Maximum number of hours of taking per day: 14
- Maximum Volume of taking per day: 79,380 Litres
- Maximum number of days of taking in a year: 120
- Earliest calendar date of taking (mm/dd): 05/01
- Latest calendar date of taking (mm/dd): 11/30
- Length of taking: 10 years
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
5775 Yonge Street
Floor 8
Toronto,
ON
M2M 4J1
Canada
Comment
Commenting is now closed.
This consultation was open from January 30, 2019
to March 1, 2019
Connect with us
Contact
Permit To Take Water Coordinator (Central Region)
5775 Yonge Street
Floor 8
Toronto,
ON
M2M 4J1
Canada
Comments received
Through the registry
0By email
0By mail
0