Cette consultation a eu lieu :
du 17 août 2021
au 16 septembre 2021
Résumé de la décision
Approval was granted to allow Mann Construction Group Ltd. to increase the allowable maximum annual tonnage that can be removed from the site, operating in the Township of Centre Wellington.
Détails de l'emplacement
Détails de l'emplacement du site
Township of Centre Wellington, Wellington County.
Part Lot 9, Concession 6, Geographic Township of Pilkington.
The site is located approximately 7 kilometres east of the Community of Elora.
The site is authorized under Aggregate Resources Act (ARA) Licence No. 5595.
A link to our mapping tool allows you to locate and view licensed sites under the ARA.
Promoteur(s)
Mann Construction Group Ltd.
7367 Wellington Road 30
Guelph,
ON
N1H 6J2
Canada
Détails de la décision
A change to Aggregate Resources Act (ARA) licence No. 5595 was approved by the Regional Director on November 19, 2021.
The licence was amended authorizing an increase in the number of tonnes of aggregate to be removed in a calendar year. The annual tonnage condition was increased from 100,000 tonnes to 300,000 tonnes annually.
Effets de la consultation
One (1) comment was received in response to the Environmental Registry of Ontario notice. The same comment was received in response to the ARA consultation process.
The comment was related to questions regarding water monitoring and operations on site. The applicant worked to address the questions by providing additional information about the site plans and water monitoring on site.
Two additional comments were received through the ARA consultation process which stated no concerns with the proposal.
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
300 Water Street, 4th Floor South tower
Peterborough,
ON
K9J 3C7
Canada
How to Appeal
Les appels ne sont pas autorisés
Ce type d’acte ne peut être porté en appel. En savoir plus sur notre processus de consultation.
Communiquer avec nous
Contact
Seana Richardson
300 Water Street, 4th Floor South tower
Peterborough,
ON
K9J 3C7
Canada
Proposition initiale
Détails de la proposition
Mann Construction Group Ltd. has applied to allow an increase in the number of tonnes of aggregate that may be removed in a calendar year. The current licence allows for the removal of a maximum of 100,000 tonnes of material annually. Mann Construction Group Ltd. has requested that the tonnage limit be increased to 300,000 tonnes annually.
This increase has been requested by the licensee to address the higher demand for aggregates in the area.
Other information
Mann Construction Limited operates the licenced site under the authority of Aggregate Resources Act licence No. 5595. In total, 40.2 hectares are currently licenced as a pit.
Public consultation opportunities
The proposal request for this licence is being circulated within the Ministry of Northern Development, Mines, Natural Resources and Forestry. Additionally, notification of this application has been forwarded to the Township of Centre Wellington and Wellington County, for comment.
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
300 Water Street, 4th Floor South tower
Peterborough,
ON
K9J 3C7
Canada
Commentaire
La consultation est maintenant terminée.
Cette consultation a eu lieu 17 août 2021
au 16 septembre 2021
Communiquer avec nous
Contact
Seana Richardson
300 Water Street, 4th Floor South tower
Peterborough,
ON
K9J 3C7
Canada
Commentaires reçus
Par l'entremise du registre
0Par courriel
0Par la poste
0