Cette consultation a eu lieu :
du 9 juillet 2021
au 8 août 2021
Résumé de la décision
The ministry has closed an application for a permit by the Corporation of the City of Pembroke to carry out sanitary sewer works in Pembroke, Ontario that would have impacted Butternut and its habitat. No decision was made and no permit has been issued.
Détails de l'emplacement
Adresse du site
Pembroke,
ON
Canada
Détails de l'emplacement du site
The works will take place along the top of slope along the Indian River between Draper Street and Munro Street.
Part of Lot 16, Concession 1
City of Pembroke
County of Renfrew
Carte de l'emplacement du site
L'épingle de localisation correspond à la zone approximative où a lieu l’activité environnementale.
Afficher cet emplacement sur une carte opens link in a new windowPromoteur(s)
The Corporation of the City of Pembroke
1 Pembroke Street West
Pembroke,
ON
K8A 3J5
Canada
Détails de la décision
The Corporation of the City of Pembroke (the proponent) applied for an overall benefit permit under clause 17(2)(c) of the Endangered Species Act, 2007 (ESA). The proposal was to carry out sanitary sewer works, including re-alignment of a sanitary sewer, in Pembroke, Ontario that would impact Butternut trees, which is a species at risk.
The ministry closed the file on April 29, 2022. No decision will be made on this application and no permit was issued.
Effets de la consultation
We did not receive any comments in response to the proposal.
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
How to Appeal
Les appels ne sont pas autorisés
Ce type d’acte ne peut être porté en appel. En savoir plus sur notre processus de consultation.
Communiquer avec nous
Contact
Carolyn Hann
3767 Hwy 69 South
Sudbury,
ON
P3G 1E7
Canada
Proposition initiale
Détails de la proposition
The City of Pembroke is seeking an overall benefit permit under clause 17(2)(c) of the Endangered Species Act, 2007 (ESA) so they can complete sanitary sewer works, including the re-alignment of a sanitary sewer, in Pembroke Ontario.
The proposal may adversely impact Butternut and its habitat, including:
- removing 2 Butternut (Category 2 and Category 3 tree)
- harming 31 Butternut (20 category 2 and 11 category 3 trees)
- impacting up to 4130 m2 of butternut habitat
Protecting species under the Endangered Species Act
Ontario provides protections for species at risk and their habitats under the ESA. Sections 9 and 10 of the ESA provide protection for individual members of a species and their habitat if that species is listed on the Species at Risk in Ontario list as either:
- extirpated
- endangered
- threatened
Butternut is listed as endangered and is therefore protected.
The main threat to the survival of Butternut trees is Butternut Canker, and this disease has affected most Butternut trees across the province.
Under clause 17(2)(c) of the ESA, the Minister may issue a permit authorizing a person to engage in an activity that would otherwise be prohibited by sections 9 or 10 of the ESA if the minister believes that:
- an overall benefit to the species will be achieved within a reasonable time through the conditions of the permit
- reasonable alternatives have been considered, including alternatives that would not negatively affect the species, and the best alternative has been adopted
- reasonable steps to minimize negative effects on individual members of the species are required by conditions of the permit
Providing an overall benefit to a protected species under the ESA means improving circumstances for the species in Ontario. Overall benefit is:
- more than "no net loss" or an exchange of "like for like"
- grounded in the protection and recovery of the species at risk
- more than mitigation measures or "replacing" what is lost
Actions to achieve an overall benefit to species
The City of Pembroke is working to identify proposed actions that would achieve an overall benefit for Butternut trees. These may involve:
- collecting 1000 seeds by qualified professionals
- making 1000 butternut seedlings available for distribution to the public for planting through local stewardship program
- archiving one Butternut deemed suitable for archiving, establishing 50 scions from that tree
- planting 14 pure butternut seedlings (in conjunction with companion tree seedlings) off site
- monitoring and tending the Butternut seedlings for at least five years
These actions are expected to achieve an overall benefit to the species by increasing the overall number of Butternut planted on the landscape, while emulating natural Butternut habitat conditions.
Reasonable alternatives being considered
The City of Pembroke has explored alternatives, including alternatives that would not adversely affect Butternut trees and their habitat. These include:
- not conducting the activity at the location specified and continue operating with broken pipeline
- Repair the broken sewer in its current location. Fewer butternut trees would be removed and harmed but there is a high probability for further emergency repairs to the sanitary sewer
- replace the sanitary sewer in its current alignment which is along the bottom of the bank of the Indian River (impacting both category 2 and 3 butternut trees (16 removed, and 40 harmed)
- new sanitary sewer alignment along the top-of-slope of the riverbank Impacting both category 2 and 3 butternut trees (2 removed and 31 harmed)
The City of Pembroke has concluded that the preferred alternative is to reconstruct the sanitary sewer in a new alignment along the top-of-slope of the riverbank, this alternative addresses concerns with the current sewer alignment, while impacting as few Butternut trees as possible.
Actions to minimize adverse effects on the species
The City is seeking ways to minimize adverse effects on the Butternut tree and its habitat. These may include:
- protective fencing for trees and marking off-site butternut trees during construction to avoid harming retainable trees adjacent to construction works
- having an inspector on-site during construction works to implement the conditions of permit and mitigation methods as required
- minimizing the construction footprint where possible
- providing all on-site personnel with Butternut identification and awareness training so they can identify Butternuts on the site and are aware of its protection under the Endangered Species Act
Other information
The Province has published a government response statement under section 12.1 of the Endangered Species Act, 2007 (ESA) with respect to Butternut.
The government response statement will be considered before a decision to issue an overall benefit permit.
A copy of the government response statement for Butternut is available at: https://www.ontario.ca/page/butternut-government-response-statement
Posting this proposal on the Environmental Registry does not imply that we will issue a permit. A permit may only be issued where the legal requirements set out in clause 17(2)(c) of the ESA have been satisfied.
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
Commentaire
La consultation est maintenant terminée.
Cette consultation a eu lieu 9 juillet 2021
au 8 août 2021
Communiquer avec nous
Contact
Todd Copeland
5520 Hwy 101 East
PO Bag 3020
South Porcupine,
ON
P0N 1H0
Canada
Commentaires reçus
Par l'entremise du registre
0Par courriel
0Par la poste
0