Il n’existe aucune obligation d’afficher cet avis sur le Registre environnemental de l’Ontario, mais nous voulons connaître votre opinion. Soumettez un commentaire et donnez-nous votre avis. Pour en savoir davantage sur le processus de consultation et les types d’avis publiés sur le registre.
Update Announcement
A decision for this proposal has been published as a Bulletin under ERO 019-2598 on November 20, 2020.
Cette consultation a eu lieu :
du 2 avril 2020
au 17 mai 2020
Résumé de la proposition
The proposal is for a new Environmental Compliance Approval for industrial ditches and stormwater management works serving Gerdau Ameristeel Corporation, located at 2025 River Road, in the City of London.
Détails de l'emplacement
Adresse du site
2025 River Road
London,
ON
N5W 6C4
Canada
Carte de l'emplacement du site
L'épingle de localisation correspond à la zone approximative où a lieu l’activité environnementale.
Afficher cet emplacement sur une carte opens link in a new windowPromoteur(s)
Gerdau Ameristeel Corporation
1 Gerdau Drive
Whitby,
ON
L1N 5T1
Canada
Pourquoi une consultation n’est pas nécessaire
On April 1, 2020, the Ontario Government made a temporary regulation to respond to the COVID-19 outbreak. Ontario Regulation 115/20 exempts all proposals for policies, acts, regulations and instruments from posting requirements under the EBR until 30 days after the declared emergency is terminated.
Détails de la proposition
The proposal is for a new Environmental Compliance Approval for industrial ditches and stormwater management works serving Gerdau Ameristeel Corporation, located at 2025 River Road, in the City of London.
The stormwater management works are comprised of stormwater quality and quantity control features to capture and contain surface runoff within the Gerdau facility site boundaries and prevent stormwater from discharging offsite. The system consists of perimeter ditches and embankments, sediment traps, and a stormwater collection pond. The pond is designed to collect storm runoff from the site during a 24-hour, 100-year design storm event plus runoff generated during a 25 mm rainfall event.
A dike has been designed and constructed along the southern property line to provide secondary containment and prevent stormwater discharge from the site during the regional storm event. There will be no permanent pool maintained in the pond and it is, therefore, considered a dry pond.
Following storm events, the pond will be pumped as needed to maintain sufficient capacity to manage storm event runoff and prevent any potential discharge from the site. The pumped volumes will be trucked by a licensed waste hauler for disposal at a City of London Wastewater Treatment Plant or similar facility.
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada
733 Exeter Road
London,
ON
N6E 1L3
Canada
Communiquer avec nous
Contact
Client Services and Permissions Branch
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada
Commentaire
La consultation est maintenant terminée.
La période de consultation a eu lieu du 2 avril 2020
au 17 mai 2020