Cette consultation a eu lieu :
du 23 décembre 2014
au 16 janvier 2015
Résumé de la décision
A permit to take water was not required.
Détails de l'emplacement
Détails de l'emplacement du site
Valerie Falls Hydroelectric Generating Station
Colin Lake 9317, Plan: 48R-3524
Township of Atikokan, District of Rainy River
District Office: Thunder Bay
Map Datum: NAD83, Zone: 15, UTM Easting: 595110, UTM Northing: 5405138
Carte de l'emplacement du site
L'épingle de localisation correspond à la zone approximative où a lieu l’activité environnementale.
Afficher cet emplacement sur une carte opens link in a new windowPromoteur(s)
Valerie Falls General Partner Limited
243 Industrial Park Crescent
Sault Ste. Marie,
ON
P6B 5P3
Canada
Détails de la décision
Amendments to the Ontario Water Resources Act (OWRA) made on April 1, 2020 removed the need for a permit to take water for the construction or operation of a dam for the purposes of generating electricity.
This activity no longer requires a permit and none was issued.
The ministry advised the applicant that no permit was required on August 26, 2020.
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
435 James Street South
Floor 3, Suite 331
Thunder Bay,
ON
P7E 6S7
Canada
135 St Clair Ave W
Toronto,
ON
M4V 1P5
Canada
How to Appeal
Appeals are not allowed
As no decision was made, there is no decision to appeal.
Communiquer avec nous
Contact
Permit to take water coordinator (Northern region)
435 James Street South
Floor 3, Suite 331
Thunder Bay,
ON
P7E 6S7
Canada
Proposition initiale
Détails de la proposition
Description of instrument
This application from Valerie Falls General Partner Limited (part of the Brookfield Renewable Energy Group) is a renewal request for Permit To Take Water No. 4365-82URGT, which is scheduled to expire January 1, 2015. The water taking will be from the Seine River at Colin Lake for the purpose of hydropower production at the Valerie Falls Generating Station location in the Geographic Township of Freeborn, District Rainy River Ontario. Details of water taking are as follows:
Permit Type: Renewal (Category 1)
Source Name: Seine River at Colin Lake
Purpose of taking: Power Production
Maximum rate per minute (Litres): 3,600,000
Maximum number of hours of taking per day: 24
Maximum volume per day (Litres): 5,184,000,000
Typical volume per day (Litres): 3,715,200,000
Maximum number of days of taking per year: 365
Period of taking: 10 years
More about Permits to take water
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
435 James Street South
Floor 3, Suite 331
Thunder Bay,
ON
P7E 6S7
Canada
Commentaire
La consultation est maintenant terminée.
Cette consultation a eu lieu 23 décembre 2014
au 16 janvier 2015
Communiquer avec nous
Contact
Permit to take water coordinator (Northern region)
435 James Street South
Floor 3, Suite 331
Thunder Bay,
ON
P7E 6S7
Canada
Commentaires reçus
Par l'entremise du registre
0Par courriel
0Par la poste
0