Cette consultation a eu lieu :
du 21 juillet 2023
au 20 août 2023
Résumé de la proposition
This proposal is for a renewal of Permit to Take Water No. 0474-9LSH8T for dewatering purposes of the Cargill Quarry. Water will be taken from one sump, located in the Unorganized Township of Sulman, District of Cochrane, Ontario, for dewatering purposes.
Détails de l'emplacement
Adresse du site
Cargill Quarry
Cochrane,
ON
Canada
Carte de l'emplacement du site
L'épingle de localisation correspond à la zone approximative où a lieu l’activité environnementale.
Afficher cet emplacement sur une carte opens link in a new windowPromoteur(s)
C. Villeneuve Construction Co. Ltd.
1533 Highway 11 West
Post Office Box No. 1720
Hearst,
ON
P0L 1N0
Canada
Détails de la proposition
This proposal is for a renewal of Permit to Take Water No. 0474-9LSH8T for dewatering purposes of the Cargill Quarry. Water will be taken from one sump at two different rates (1. initial rate - during the start of season to remove water that accumulated over the winter, and 2. maintenance rate - for on-going dewatering requirements for the remainder of the season) located in the Unorganized Township of Sulman, District of Cochrane, Ontario. Details of Water Taking are as follows:
Purpose of water taking: dewatering - pits & quarries
- source of water: Cargill Quarry Sump (initial dewatering)
- maximum rate (litres per minute): 2,720
- maximum number of hours of taking per day: 24
- maximum volume (litres) per day: 3,917,000
- maximum number of days of taking in a year: 45
- period of water taking: June 20 to August 3 for 10 years
Purpose of water taking: dewatering - pits & quarries
- source of water: Cargill Quarry Sump (maintenance dewatering)
- maximum rate (litres per minute): 500
- maximum number of hours of taking per day: 24
- maximum volume (litres) per day: 720,000
- maximum number of days of taking in a year: 90
- period of water taking: August 4 to October 10 for 10 years
There are 3 categories of a Permit to Take Water:
- Category 1: water takings are anticipated to have a lower risk of causing an unacceptable environmental impact/interference
- Category 2: water takings are anticipated to having a higher potential of causing unacceptable environmental impact or interference
- Category 3: water takings are anticipated to have the highest potential of causing unacceptable environmental impactor interference
The proposed water taking qualifies as a Category 1 permit.
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
135 St. Clair Avenue West
Floor 1
Toronto,
ON
M4V 1P5
Canada
Communiquer avec nous
Contact
Client Services and Permissions Branch
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada
Commentaire
La consultation est maintenant terminée.
La période de consultation a eu lieu du 21 juillet 2023
au 20 août 2023